Are time-and-materials contracts and labor-hour contracts considered fixed-price contracts?

Enhance your preparation for the Certified Radiology Administrator Test. Explore flashcards and multiple-choice questions with hints and explanations. Ace your exam with confidence!

Time-and-materials contracts and labor-hour contracts are not considered fixed-price contracts. In a fixed-price contract, the price is set at the outset and does not change regardless of the actual costs incurred during the project. This provides a level of certainty regarding budget and expenses for both the buyer and seller.

In contrast, time-and-materials contracts involve payment based on the actual time spent by workers and the materials used, which can fluctuate and lead to variable costs. Similarly, labor-hour contracts are based on the number of hours worked, which also makes the overall price unpredictable. These arrangements introduce a degree of uncertainty as labor costs can vary based on the number of hours worked and the rates charged, contrasting sharply with the set price approach that characterizes fixed-price contracts. Therefore, the correct answer reflects the nature of these contracts accurately.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy